Overall Scope
1) Drywall walls at Shop (dettached Garage), insulation by others see pictures, some are full height some are half height with CMU Base. Tape in preparation for orange peel texture and paint.
http://g2h3.blogspot.com/2012/01/g2g2-detached-garage-current-status.html
2) Drywall upper half of attached garage, insulation by other see pictures
http://g2h3.blogspot.com/p/garage-attached.html
3) Drywall around steel support beam in garage to make it clean, wood framing already in place.
4) Drywall one closed off door opening at basement hallway
5) Drywall around lower half of home office in basement, included new half height wing wall
6) Drywall above basement fireplace where rock was removed.
7) Drywall above upper floor fireplace where rock was removed.
8) Drywall on bottom sides of steps and landing in closet on basement level
Friday, January 13, 2012
Tuesday, January 10, 2012
G2G2 the Detached Garage Current Status
This will all be insulated and drywalled, then textured and painted. Once it gets warm we will Epoxy or Oil Paint the CMU Block and the Concrete using a textured non slip additive.